Project information

  • Category: Biomass
  • Client: Amphan Biomass Power Plant, Buriram, Thailand.
  • Commercial date: July, 2017
  • Install Capacity: 9 MW Steam Turbine Generator

Site condition;

The Project is located in Buriram, Thailand. with turbine output each unit 9MW. The offered is complete of revamp biomass boilor, combustion system, ash handling, pressure part, air preheater and combustion air system, exhaust stack, ESP system, steam turbine, generator, gearbox, steam condensor, coooling tower, electrical system and fule feeding unit.

The balance of plant system complete replacement and revamp the feed water system, automation and SCADA system, MV switchgear, transformer and protection system.