Project information

  • Category: Cogeneration
  • Client: Enesol Co., Ltd. Thailand
  • Commercial date: Decemer, 2011
  • Install Capacity: 5.5 MW Gas Turbine Generator

Site condition;

The Project is located in Saraburi, Thailand in Thai German Ceramic Industry factory with gas turbine output 5.5MW ISO condition. The offered is complete of Erection of gas compressor unit, Gas turbine and generator package, Inlet and ventilation duct system to complete the gas turbine generator unit.

The balance of plant system complete with exhaust gas duct work to connect via spray dryers, control and measurement the flue gas system, complete control protection system.

This application is utilize the exhaust gas from gas turbine to dry sand sludge in atomizing process in spray dryer unit. The product from this process can be formed raw materila for ceramic tile.